IAA to Implement RPKI
Those of you who attended the Life under Lockdown session will have seen the following timetable for IAA’s implementation of RPKI:
Milestone | When |
Metrics and reporting to members | Now |
RS1 Upgrades | 17th – 18th August, 2020 |
RS2 Upgrades | 24th – 25th August, 2020 |
Route Server Automation (including AS – SET updates | 1st September, 2020 |
Drop invalid routes | 1st September, 2020 |
We are keen to meet these dates and hope you will all see the benefits of a cleaner routing table. Check out Nick Pratley’s presentation from the event which includes a listing of the routes we will drop, or use lg.ix.asn.au to see what routes are being advertised.
Please let us know if you want more information or need further assistance with the routes we have flagged as invalid. Email peering@ix.sn.au